Stage 5

Plan and pilot

What gets done, in what order, with whom and how is it tested?

Measure and decide, test and scale

Objective
Turn the value case and the gaps into a plan with owners, dates, budget and funding source, and into a pilot that tests the model with a real customer.
Time
MSME: 1 week of planning. Pilot: P1 at the end of month 3 and P2 in month 12. Large company: 2-3 weeks of planning. Pilot: P1 at the end of month 3 and P2 in month 9.

Purpose of the stage

The decision in this stage

In this stage you decide what gets done, in what order and with whom, and which pilot tests the model. Stages 2-4 said which opportunity is worth pursuing, how much money it creates and what is missing to capture it.

Here you put all of that in order over time and test it at a small scale. The plan includes a pilot with a customer, a partner, an indicator and a date.

Stage 5 ends when the pilot starts, and what happens during the pilot is measured in Stage 6.

Minimum to move forward: in an MSME, H11 and the pilot with its indicator and its H06 baseline.

In the region

With expensive capital, each pilot must risk little and teach quickly. The lessons of a public business support program in Peru point the same way: an internal champion, business language, a realistic exit and visible moments of achievement.

Step by step

Tasks and deliverables of each step

  1. 01Bring together the results of Stages 2-4The prioritized opportunity, the value case and the gap map across its six fronts, money included, in a session of the owner with the team.Inputs: H01, H02, H03, H12, H04, H08, H09 and H10. In the book: section 5.2
  2. 02Write the activities by dimensionCulture, technology and AI, capabilities, ecosystem and synergies, and finance. Each gap from Stage 4 becomes at least one short- or long-term activity.H11, template in section 5.4. In the book: section 5.3
  3. 03Assign owners and phaseOne responsible function per activity. Place it in the pilot phase: Phase I (prototype and unpaid pilot), Phase II (paying customer) or Phase III (scale).H11, template in section 5.4
  4. 04Give each activity a budget and a sourceFigures from H02 and the instrument from H10. Keep own cash separate from what depends on winning a competitive call.H11, Finance dimension. In the book: section 5.5
  5. 05Set milestones and decision datesFirst pilot, first paying customer, first synergy in operation. Mark which ones require a decision by someone with authority (gates P1 and P2, section 5.6).H11, calendar in section 5.4. In the book: section 5.6
  6. 06Design the pilotOne customer, one partner, one indicator and one date, with success criteria written before starting (section 5.7).Indicator and baseline: H06. Expected margin: H02. In the book: section 5.7
  7. 07Approve it and review it every quarterAn MSME, with the owner. A large company, in the management committee or the board. It is reviewed every three months with what has been learned.H11, quarterly review with management. In the book: section 5.8

Tools

Templates to work on as you go

H11 Book, 30-45 min

Transformation roadmap

Brings the results of the other tools together into a phased plan.

  1. Summarize the key activities by dimension, with their estimated time.
  2. Define dated milestones: first pilot, first customer, first synergy.
  3. Assign a responsible function and place each activity in one of the three phases.
  4. Review the roadmap every quarter with management.

Result Activities and milestones in two parts, and owners by phase.

In the book: section 5.4Template and view in the book

By company size

How the work changes in an MSME and in a large company

MSME

  • Days 1-30: written agreement with a buyer, minimum equipment installed and a daily log of kilos, price and destination.
  • Days 31-60: run the pilot and sell the first batch with a shipping guide and a certificate.
  • Days 61-90: gate P1 with the owner. If it passes, apply for co-financing with the pilot data.

Large company

  • Days 1-30: the board approves the roadmap and the budget. A dedicated team is named and the agreement with the partner is signed.
  • Days 31-60: pilot on one line or plant, with a weekly dashboard of the indicator.
  • Days 61-90: gate P1 and changes to the targets and bonuses of the areas involved. The committee reviews in month 6.

Common mistakes

  • A pilot with no decision date. It drags on until nobody remembers what it was testing.
  • Scaling before the gate. Buying the plant before the customer pays turns a pilot into debt.
  • Testing everything at once. Submodels on different flows in the same pilot make it impossible to know which one worked. One opportunity per round, and the others on the short list wait.
  • Leaving incentives untouched. If sales is paid by volume, the service model never reaches the customer.
  • Sustainability cut off from results. The circular target must be owned by whoever is accountable for the line's margin.

Deliverable

When the stage closes there is an approved roadmap and a pilot under way

Deliverable

Roadmap in H11, approved, with activities, owners, dates, budget and source, and a pilot with customer, partner, indicator, success criteria and decision date.

To move on to stage 6

  • Each gap from Stage 4 has at least one activity with an owner.
  • Each activity has a budget and a source of money.
  • Each applicable barrier, out of the nine, has a measure, a control signal and a gate in the roadmap.
  • There is at least one change to a target, bonus or internal price in the roadmap.
  • The pilot has a customer, a partner, an indicator with a baseline and a date.
  • The criteria to scale, adjust or close (section 5.6) are written and approved.