Illustrative case, responsible mining, large company
Copper mine, southern Peru
Retreading pays for the water the tariff does not, and the case is viable with equity.
Viable with equity
- USD 728 K
- NPV with equity
- 12.9%
- IRR
- 6.7 years
- Payback
Capital scenarios
The capital that makes it viable
Assumptions and detail
Company and operation
- Company
- Fictitious open-pit copper mine. 60 haul trucks and 360 tire positions
- Location
- Southern Peru, an area with low water availability, as context
- Flow
- 400 tires of size 59/80R63 a year, about 1,600 t, and a concentrator processing 60,000 t per day
Case built with the Playbook tools from public data for the region. It does not represent a real company.
Calculation assumptions
USD, 10% rate, 10 years, Peru income tax of 29.5%. Payback with equity: 6.7 years. Impact loan for 70% of the project, at 7.5% a year in USD, over a 5-year period with a 6-month grace period, assessed with the adjusted NPV.
Path through the stages
- Prepare
Maintenance leads with the project charter, and procurement joins the team from day one
- Diagnose the value chain
400 tires a year, about 1,600 t, leave with a sound casing
- Choose opportunities
4.4 retreading, 3.3 performance as a service and 5.6 circular water
- Build the value case
NPV of USD 0.73 M with equity. Water reduces value
- Measure gaps
Procurement must contract on cost per hour and track the hours of each casing
- Plan and pilot
60 retreads on ten trucks, with the committee business case milestone in month 12
- Measure, scale and adjust
N8 falls from 1,600 to 1,374 t and N2 rises to 45%
Rerun the calculation with your own figures
Spreadsheets H02 and H06, used to build the case, come with the Kit. In Spanish.